| Kenniscentrum DSSS | ![]() |
|||||||||||||||||||||||||||
![]()
Written by:
Bart van Gils
Maritiem Instituut "De Ruyter"
Table of Contents
1. Introduction.
1. Introduction
The Norstream and the Norsky run a daily service between the United Kingdom and Zeebrugge (Belgium). Our contacts on these ships are the two Chief Engineers with whom we had good rapport.
For the project it was necessary to collect general data of the hot water system design and flow path. In previous reports no general drawing of the equipment of the system has been provided. The Hydrosmart unit is externally wound around the water supply pipe, feeding the steam hot water heater aboard the Norstream.
A schematic of the system is as follows:
The drinking water for consumption on the vessel is bunkered in the port of Zeebrugge or Hull. The water is local mains supply which is relatively hard water with many minerals and salts.
1.2 Technical specifications of the heater
The water is heated by steam, this steam condenses.
![]() Hydrosmart installed aboard the Norstream The exchanger aboard the Norsky was cleaned on 27th of October 2005. Hereafter the system was again put back into usual operation. On the 12th of January 2006 an email was sent to both ships asking if there were any problems developing with the heater of the hot water system. The Norsky have then responded advising that the water remains at the correct temperature on high loads, and the heater has not been polluted with scale. The Norstream also reported that no problems had occurred. After another month, around the 12th of February 2006, problems occurred with the heater aboard the Norsky. At high loads, the temperature of the hot water fell. The engineers suspected that there was a high build-up of scale on the tube stack. The heater was then opened up and photographs taken of the elements which had scaled up significantly. In the two pictures below you will see the diameter of the scale around the pipes was about 3 mm.
![]() Heat Exchanger aboard the Norsky, 12th of February 2006
The Norstream was visited in the port of Zeebrugge on Monday 22nd of May 2006.
![]() Opening of the Heat exchanger aboard the Norstream
The difference in scale on both exchangers is to be seen clearly on the photographs provided. The exchangers were both cleaned in the same week to commence this trial, providing identical situations at trials commencement. The bunkering with mains water at each port was not controllable, but it is assumed the water quality was of the same source of supply in both vessels at the time of bunkering. Considering the ships are of the same type and on the same shipping lane we assume this to be consistent to both vessels. We can therefore conclude that the Hydrosmart treatment extends the time between cleaning of heat exchangers on these vessels and lowers maintenance problems very certainly. Filled in truthfully,
Bart van Gils Michiel Gronheid Peter Verstraete
Flushing, 14th of June 2006
| ||||||||||||||||||||||||||||
![]() |
||||||||||||||||||||||||||||









